Kumba Resources (Pty) Ltd

The complete design, supply and erection on a turnkey basis, of a plant to treat 220 000 tons per annum of titanium dioxide slag at TRICOR’s Central Processing Complex at Empangeni, in KwaZulu Natal. The plant design has been refined through test work and the application of new technologies to reduce the generation of fines in the process and improve the product specifications. The plant consists of primary crushing, drying, milling, classification, product storage and load out, dust extraction and general materials handling.

  • Service Provided: EPCM Service (engineering, procurement, construction & management)
  • Project: Titanium Dioxide Slag Treatment Plant
  • Contract value: US$ 5 million
  • Date: Completed June 2003 (Duration 18 months)
Kumba Resources (Pty) Ltd